⏱️ T-Minus Timeline & Cutover Sequence

What happens when you click

T-12 months β€” Discovery

Flow

T-12mDiscovery
➜
T-6mLanding zone
➜
T-4wReplication
➜
T-048-h cutover
➜
T+14dHypercare
Click a node to learn what it does.
    Milestone JSON from the API appears here.

    Deep dive

    How

    • Work backwards from the lease end: fix T-0 per wave, then lay out discovery, landing zone, replication and rehearsal.
    • Keep a 2-week hypercare buffer before the next wave.

    Why

    • A T-minus plan makes dependencies visible: no replication without a landing zone, no landing zone without a network design.

    When

    • Publish at T-9 months; re-baseline after the pilot at T-6.

    Pitfalls

    • Starting replication before Direct Connect/ExpressRoute is live (lead time is weeks).
    • Skipping the dress rehearsal.
    • Ending hypercare too early β€” most firewall misses appear at month-end batch runs.

    Key ideas

    The 48-hour cutover window

    Friday 8 PM stop traffic Β· Saturday 2 AM final DB delta Β· Saturday 10 AM DNS cutover + smoke tests Β· Sunday 12 PM business sign-off. Everything else in the programme exists to make these 40 hours boring.

    MovereCloudamizeLanding zoneDress rehearsalHypercare